How can I add funding totals per year in Project across an activit

C

Carlos

I would like to maintain/show cost per year per activity and totals per year
at the bottom.
 
J

Jan De Messemaeker

Hi,

Everything is possible, except totals at the bottom: Project makes totals at
the top.
In Task Usage, create a timescale with the minor scale years (this also the
middle scle years)

Then Tools, Options, view, click on Project Summary task.
HTH
 