I'd like to push ahead all tasks 1 month. How can I do this?
-david
 
J

Jan De Messemaeker

Hi David,
As long as you haven't introduced any actuals, you have to run the Adjust
Dates macro (P98) or the Adjust Dates add-in you can activate from the
analysis toolbar (P2000+)
HTH

--
Jan De Messemaeker