How can I Change Values in Who Does What Report?

T

Todd

Can someone please tell me how to change the vaule in the work column to show
days not hours?

Thanks!

-Todd
 
J

JulieS

Hi Todd,

The Who Does What report is using the default value (Hours) for work
that is set on the Schedule tab of the Tools > Options dialog box. Go
to Tools > Options, Schedule tab and change the choice "Work is entered
in:" to Days. Your report should now show the work value expressed as
days.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 