How can I do this?

G

Gordowey

Hi all

I have:

[---------Task 1--------------][**************** Task 2
*************************] [Milestone1]

I need to adjust Task 2 duration automatically, depending on the
finish date of Task 1, and the Starting date of M1

please help me

Thanks

Alberto
 
G

Gordowey

Hi Gordowey,

It sounds as though you are looking to create a hammock task. For
details on how see FAQ 19 "Hammock Tasks" at:http://project.mvps.org/faqs.htm

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visithttp://project.mvps.org/for the FAQs and additional information
about Microsoft Project




[---------Task 1--------------][**************** Task 2
*************************] [Milestone1]
I need to adjust Task 2 duration automatically, depending on the
finish date of Task 1, and the Starting date of M1
please help me

Alberto- Ocultar texto de la cita -

- Mostrar texto de la cita -



Thnak you very much, that was what I needed
regards
Alberto
 