Go to the insert menu and insert the baseline start or baseline finish
column.
Any tasks with "NA" in this column do not have a baseline.
You can use the autofilter function (find it on the "project" menu /filtered
for / then look at the end of the pull down menu) to filter the view to just
show the non-baselined tasks.
--