How can I find out if all the tasks in the schedule are baselined?

N

nan

I inherited some project schedules and I don't know if all the tasks in the
schedule are baselined. How can I find out?
 
J

JackD

Go to the insert menu and insert the baseline start or baseline finish
column.
Any tasks with "NA" in this column do not have a baseline.
You can use the autofilter function (find it on the "project" menu /filtered
for / then look at the end of the pull down menu) to filter the view to just
show the non-baselined tasks.
 
N

nan

Thanks!

JackD said:
Go to the insert menu and insert the baseline start or baseline finish
column.
Any tasks with "NA" in this column do not have a baseline.
You can use the autofilter function (find it on the "project" menu /filtered
for / then look at the end of the pull down menu) to filter the view to just
show the non-baselined tasks.

--
-Jack ... For Microsoft Project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
 