A
adamt8
Here is the scenario:
A task (like a daily mtg or activity) needs to happen throughout a project.
A recurring task would seem to accomplish this.
Set start and end dates.
However, when the critical path pushes the project end date out, the task
does not "stretch". I have also tried this with a single task, but the same
problem.
I would prefer the single task, because then I can assign a resource.
If there is a better way to accomplish the scenario, I'm ok with that too.
A task (like a daily mtg or activity) needs to happen throughout a project.
A recurring task would seem to accomplish this.
Set start and end dates.
However, when the critical path pushes the project end date out, the task
does not "stretch". I have also tried this with a single task, but the same
problem.
I would prefer the single task, because then I can assign a resource.
If there is a better way to accomplish the scenario, I'm ok with that too.