How can I mark a task uncompleted without erase it?

L

LilianaGO

I have a project that have some task uncompleted because they was canceled.
I don't want erase that tasks because report some hours of work but the
reported hours is not the total. How can I manage it without erase in the
form that the percent completed of my project present 100%?
 
M

Mike Glen

Hi Lilian,

Welcome to this Microsoft Project newsgroup :)

Don't make the task 100% complete, let Project do that for you. Just enter
the actual work and enter zero for the remaining work.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 