I have a project that have some task uncompleted because they was canceled.
I don't want erase that tasks because report some hours of work but the
reported hours is not the total. How can I manage it without erase in the
form that the percent completed of my project present 100%?
I don't want erase that tasks because report some hours of work but the
reported hours is not the total. How can I manage it without erase in the
form that the percent completed of my project present 100%?