how can I put a task on hold

R

RTucker

Enter a date in the "Resume" task field.

From MSP Help:
The Resume field shows the date that the remaining portion of a task is
scheduled to resume after you enter any progress, for example, % Complete, %
Work Complete, Actual Work, Actual Duration, or Actual Start. The Resume
field is also recalculated when the remaining portion of a task is moved to a
new date.
 
J

Joe

That's interesting, I never heard of this field before. Where is it? I
don't see it anywhere on the Task Info dialog box.

Joe
 