Enter a date in the "Resume" task field.
From MSP Help:
The Resume field shows the date that the remaining portion of a task is
scheduled to resume after you enter any progress, for example, % Complete, %
Work Complete, Actual Work, Actual Duration, or Actual Start. The Resume
field is also recalculated when the remaining portion of a task is moved to a
new date.