How can I schedule tasks to have start & finish times vs. dates?

M

MD3

I am attempting to schedule a project that occurs all on one day thus the
hours and minutes are my durations. I have setup the timeline and durations
correctly but I can get the start and finish columns to change from dates to
times? I can be the only one that has ever need to do this? Please
advise.... Thanks! MD3
 
J

JackD

Go to tools menu / options / general tab and choose a date format which has
hours and minutes.
 