T
tigerfan
In instances where I have multiple predecessors for a task, I want to be able
to see which predessor is driving the task.
to see which predessor is driving the task.
Jan said:Hi Tigerfan,
Jack Dahlgren, fellow MVP, has developed a great macro doing what you want
and more.
Look for the trace macro in
www.masamiki.com
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
JackD said:Not always.
There are a few cases where this is not true.
1) When there are more than one tasks with 0 free slack. Free slack is
dependent on successor tasks so if a task has two successors and one is
earlier than the task you are looking at, it may have 0 free slack, but
still have a gap between when it finishes and when the next task starts.
2) When you have linked project summary tasks. In this case, the task may be
driven by the start date of the summary task, yet there is no explicit
dependency to the task itself. This is one of the reasons that linking to
summary tasks is discouraged. This sort of dependency can be a little tricky
to debug.
davegb said:I don't have Project here to play with this, so I'm picturing it in my
mind. (I also answered this rather quickly this morning, and remember
thinking, "Are you sure...." as I entered it.)
I think you're describing a scenario with negative slack, in which case
you'd be correct. Since I always correct negative slack conditions, I
wasn't thinking of that situation.
Anyone who has had any training knows better than to link summary tasks
EVER! I admit, we don't know the skill level of the OP, so it's worth
mentioning. I assumed (always a mistake) that the OP would know better.
JackD said:Dave, no negative slack required.
Task X has tasks A and B as predecessors.
Task A is on Monday and has two successors X and Y. Task Y starts Tuesday.
Task B is on Thursday. Task X is on Friday.
Task A has zero free slack. Task A does not "drive" Task X.
I never say never and I always refrain from saying always. This stuff is
allowed by project and thus it happens. Sometimes by good people. Sometimes
on purpose. It is unwise to assume that everyone follows whatever rules you
happen to favor. This means that absolutes may be poor advice or at least
inaccurate.
-Jack
davegb said:Thanks for telling me I should favor the rules you favor instead of the
rules I favor. Frankly, I don't favor this!![]()
You're missing an important point, Jack. It's called Critical Path
METHOD, keyword here, METHOD. When you use a methodology, you don't do
it your way and I do it mine, particularly if either of our ways gives
false results.
Not linking summary tasks is not an opinion, though many
people think it is. Those of us who know it doesn't work are probably
being overly polite to those who don't fully understand CPM. So I'll
say it straight up here, DON'T EVER LINK SUMMARY TASKS! See, I say
never sometimes, and I mean it.
Of course, you can link summary tasks in Project. You seem to think
that since it can be done, we should allow for it. I disagree.
OK.
Not when
it screws up getting a meaningful critical path, which, sooner or later
it does. I can get circular references in Project, but I don't advise
people to do it.
I try to be flexible about rules in most instances. But when flexible
means getting misleading results, it's time to get inflexible.
One of the nice things about this NG is that most of the time, when we
see things differently, we just agree to disagree. However, when
someone starts telling someone else how to post, they're overstepping
their bounds.
How about we just agree to disagree, and I'll post what I
believe is in the best interests of the OP, and you do the same?
JackD said:That certainly wasn't my intention.
Is it the method or problems with the tool that give false results?
Is the use of Project limited to those who practice CPM? I know some people
think it should be, the fact is that it isn't. Project is perfectly happy to
let you drag and drop your tasks all over the place with no care of how they
relate to one another. I THINK this is by design rather than by accident.
Some people actually have schedules which are non-deterministic in which
task to task dependencies are counter-productive.
If it came across as me telling you how to post, then I apolgize.
That truly was not my intention. I thought that the tone of my post was
humorous...
Certainly. Take a look at what I wrote you and you can see that I was not
advocating the linking of summary tasks but was discouraging the use of them
and giving a reason why.
"There are a few cases where this is not true.
...
2) When you have linked project summary tasks. In this case, the task may be
driven by the start date of the summary task, yet there is no explicit
dependency to the task itself. This is one of the reasons that linking to
summary tasks is discouraged. This sort of dependency can be a little tricky
to debug."
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.