P
pebbles
MS Project 2003
I need to be able to run a cross-tab report, but using "remaining work"
rather then work, actual work, etc. I cannot seem to add this field, even
though I would assume that it is held on the same table.
I need to be able to run a cross-tab report, but using "remaining work"
rather then work, actual work, etc. I cannot seem to add this field, even
though I would assume that it is held on the same table.