Dear MPP users,
There has been a question posted with exactly the above subject - I
was unable to continue that thread therefore I'm starting a new one. I
apologize for the inconvinience.
I use MPP 2007 and I have this exact problem -
I filter my schedule for "Resource Usage" or "Task Usage" view.
1. I want to add 'remaining work' manually for a task (this task is
not yet complete)
2. When I add 'Work' (we all know 'remaining work' is not available as
a timephased filed) in the timephased view, one of the following
happens -
a) The work hours gets added to the 'Actual Work' also
b) The 'remaining work' gets added at the end of the schedule, not
exactly on the day I want.
c) The exact 'remaining work' does not get added. I enter 4, and
3.85 gets added.
Can some one help? I'm really stuck. Automatic leveling is freezing
the MPP and manual leveling is not possible because of the above
mentioned issue.
Thanks,
Prashanth
There has been a question posted with exactly the above subject - I
was unable to continue that thread therefore I'm starting a new one. I
apologize for the inconvinience.
I use MPP 2007 and I have this exact problem -
I filter my schedule for "Resource Usage" or "Task Usage" view.
1. I want to add 'remaining work' manually for a task (this task is
not yet complete)
2. When I add 'Work' (we all know 'remaining work' is not available as
a timephased filed) in the timephased view, one of the following
happens -
a) The work hours gets added to the 'Actual Work' also
b) The 'remaining work' gets added at the end of the schedule, not
exactly on the day I want.
c) The exact 'remaining work' does not get added. I enter 4, and
3.85 gets added.
Can some one help? I'm really stuck. Automatic leveling is freezing
the MPP and manual leveling is not possible because of the above
mentioned issue.
Thanks,
Prashanth