Timephased remaining cost....

  • Thread starter R.Scott Fleming
  • Start date
R

R.Scott Fleming

Is there a way to see the remaining cost of a task as it is distributed over
the remaining duration of the task. I would like to see this information
while in the task or resource usage view.
 
R

Rod Gill

Yes, the Cost Field is the remaining cost for all dates in the future as
there shouldn't be any completed work in the future (it should all be moved
back in time to when it was actually done).

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
R

R.Scott Fleming

Thanks Rod, I seemed to have missed the obvious...The schedule requires
input to manage the work to date (updating %complete or actual hours) and
then updating the remaining work to the correct dates (ie. work goind forward
from current date)

I appreciate your help!!!
 
D

Derekl001

Can the remaining costs be shown timephased from the Status Date onwards ?
Kind regards,
Derek
 
R

R.Scott Fleming

I believe the only way this can be done is to move the unfinished portion of
the task to the status date.
 