How do I assign capital expense to a task?

K

Kathy

Some tasks in my project plan can be capitalized, while others are directly
expensed. How can I assign capital expense to a task?
Thank you.
 
M

Mike Glen

Hi Kathy,

Welcome to this Microsoft Project newsgroup :)

View the Cost table and enter the expenses in the Fixed Cost column.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 