How do I assign work for 6:00 PM to 6:00 AM in Project?

L

LostProjectManager

I cannot get Project to accept my night time crews schedule of 6:00 PM to
6:00 AM. HELP!
 
N

Nick Miller

Within MSProject Professional, select Tools\Options\calendar and modify the
default working times.

Let me know how this goes.

Nick
 
J

JulieS

Hi LostProject Manager,

The calendar times need to be entered so they don't span over 12:00 am
(midnight.) For example, if the night crews start work on Sunday night at
6:00 pm and finishes the shift at 6:00 am on Monday:
Choose Tools > Change Working Time to open the Change Working Time dialog
box.
Select all Sundays by clicking on the column heading for Sunday.
Enter 6:00 pm in the From: box. Enter 12:00 am in the To box.
Then select all Mondays by clicking the "M" column heading.
Enter 12:00 am in the From box and 6:00 AM in to To box (first row.)
In the next row down enter 6:00 pm in the next From box and 12:00 am in the
To box.

You may want to take a look at the "Night Shift" base calendar in the Change
Working Time dialog box for some guidance.

Hope this helps. Let us know how you get along.

Julie
 