How do I calculate difference (measured in days) between 'Actual .

M

Morten H.

I would like to calculate the difference (measured in days) between the
fields 'Start' and 'Actual date' in order to setup Graphical warning on
overdue tasks.
 
G

Gérard Ducouret

Hello Morten
Try the following formula, in a number x field :
Tools / Customize / Fields.../ Formula...
ProjDateDiff([Baseline Start];[Actual Start];[Project Calendar])/[Minutes
Per Day]
Then:
Tools / Customize / Fields.../ Graphical Indicators...

Gérard Ducouret
 