N
newbeingirl
In Microsoft Project it is set up so that each day is an 8hr. work day and
the week then totals to 40hrs. I was wondering if there was a way to change
it so that it just recognizes the whole 40hrs as a total and not divided on a
daily basis. For example if someone works for 10 hours a day and takes off
friday, is there any way to change it so that Microsoft Project doesnt see
the 10 hours a day as a full day and 2 hours over time?
the week then totals to 40hrs. I was wondering if there was a way to change
it so that it just recognizes the whole 40hrs as a total and not divided on a
daily basis. For example if someone works for 10 hours a day and takes off
friday, is there any way to change it so that Microsoft Project doesnt see
the 10 hours a day as a full day and 2 hours over time?