How do I correct the Week in Timescale View?

N

Noelle

I am using Project 2003 with Project Server, this year (2009) I have an issue
where the Timescale showing "Weeks" is out by one week. Today being 21st Jan
should be in Week4 according to our business calendar but Project shows it as
Week3. I have tried toggling "fisical year" option to no avail.

Thanks in advance for your help
Noelle
 
D

David Hans

Hi Noelle,

You could try going to Tools, Options, Calendar and set the "Week starts on
Monday" instead of the default Sunday.

I have a plan with week numbers and week 1 for me starts in 29th December
2008.


regards,
David.
 