A
Andy Gray
I am looking to level resources that are both over and underallocated.
Whilst one resource is working on more than one task, I reduce the effort on
both tasks to avoid over allocation. When one of the tasks has been
completed I would then like to increase the effort on the reaining task to
ensure that the resource is working at max capacity and that the task is
completed in the shortest time possible. How do I get Project to do this?
Whilst one resource is working on more than one task, I reduce the effort on
both tasks to avoid over allocation. When one of the tasks has been
completed I would then like to increase the effort on the reaining task to
ensure that the resource is working at max capacity and that the task is
completed in the shortest time possible. How do I get Project to do this?