How do I extend the calendars for dates before 1/1/84?

R

Ridgeroad

I wish to undertke some historical analysis - and require the calendars to
cope with dates from 1962 through to 2006. The current configuration of the
MSProject calendars limits dates to between 1984 and 2049. Is there a way of
extending the calandar range?
 