How do I find the paths in Project?

S

Stan R.

I need to determine identity of each path through my project. Is there a
short, built-in way to do this in Project?
 
C

Catfish Hunter

Sorry to say the answer is no. Unlike P3 you can not easily trace a path
through your schedule. You can double click on each predicessor, write down
the finish date then decide what is driving your task. You can use the F5
button to jump to that task. Good Luck.
 
R

Rod Gill

One way is to click Window, Split
Then Right-Click in the lower form and select Predecessors and Successors.

Now you can click on a task above and see all predecessors and successors.

The Network diagram gives you another view of all links and finally there
are a number of macros floating around the Internet that show paths.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top