R
rlglaxton
To any bright MS Project superuser -
I have many workshops planned as tasks in a complex project. They run a
full day (8 hours) each. As I change or add tasks & Ms Project recalculates
my schedule, I need each workshop to begin & end the same day, without having
to go through hundreds of lines and manually constraining each one each time.
How can I notify MS project that these particular tasks must not be split
across 2 days?
thanks
I have many workshops planned as tasks in a complex project. They run a
full day (8 hours) each. As I change or add tasks & Ms Project recalculates
my schedule, I need each workshop to begin & end the same day, without having
to go through hundreds of lines and manually constraining each one each time.
How can I notify MS project that these particular tasks must not be split
across 2 days?
thanks