how do I import multiple resources for a task in project?

B

Brad

How can I import multiple seperate resources that apply to a task in MS
Project? I can import a single resource per task quite easily but have not
been able to find a method to import more than 1 seperate resource per task.
 
J

Jan De Messemaeker

Hi,

There are a number of ways to attach resources to a task.

You can double-click the task line and in task information, resources pad,
enter all the resources
Or in a task view, you can activate the Assign resource icon, select the
resources needed in the Assign resources window, then click assign
Or you can write the resource names, separated by the list separator, in the
resource names field

Each of these methods has particular methods in case you do not need exactly
100% of the resource.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Brad said:
How can I import multiple seperate resources that apply to a task in MS
Project? I can import a single resource per task quite easily but have not
been able to find a method to import more than 1 seperate resource per
task.
 