How do I include the task name for every subtask listed in Project

  • Thread starter Reporting task and subtask together
  • Start date
R

Reporting task and subtask together

I want to modify the who does what report to show the task associated with
each subtask. How do I do that?
 
J

John

Reporting task and subtask together <Reporting task and subtask
I want to modify the who does what report to show the task associated with
each subtask. How do I do that?

Together,
The simple answer is, you can't. When you say, "...the task
associated...", I assume you mean the summary line which isn't really a
task at all.

The "Who does what" report is analogous to the Resource Usage view which
technically shows Resources and Assignments, not Resources and Tasks (or
subtasks if you will).

The only way you can get the exact report you want is by exporting the
data to another application (e.g. Excel) and creating the format there.

John