how do I link MS project and outlook calendars

M

Mark Pi Tech

I am wondering if it is possible to link an employees outlook calendar with
his corresponding MS project resource calendar, such that it imports holidays
etc automatically.
 
R

Rob Schneider

Mark said:
I am wondering if it is possible to link an employees outlook calendar with
his corresponding MS project resource calendar, such that it imports holidays
etc automatically.

Not practically possible, but possible with the help of a cleaver
programmer who knows Microsoft Office application development technology.
 
D

davegb

Rob said:
Not practically possible, but possible with the help of a cleaver
programmer who knows Microsoft Office application development technology.

I used to work with one of those "cleaver" programmers, and he wrote
cutting edge code! :)
 
R

Rod Gill

You can only do it with code. However you would have to be very careful what
you brought across because it would have a big and not necessarily accurate
affect on your schedules.

Better yet is a separate tool that updates all schedules with periods you do
want removed from Standard Calendars.
 