how do I lock a task id number in ms project?

E

erin

I would like to lock the task id's in my schedule so that they do not
renumber themselves every time a task is added. Is there a way to do this?
 
J

JulieS

Hi Erin,

Try using the Unique ID field. It functions as you need.

I hope this helps. Let us know how you get along.

Julie
 