How do I open all subtasks in a MS-Project in one operation?

T

Tom Uleman

I'm working with a large project planning in MS-Project. Sometimes I want to
see subtasks. Opening them one by one is a lot of work. I would like to know
if it's possible to open all subtasks in one operation.
 
J

JulieS

Hi Tom,

Try using the "Show" button on the Formatting toolbar and select "All
Subtasks"

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top