I am trying to assist somebody beginning a project who wants to use an old
project as a basis. He already went through the plan and manually adjusted
dates. However, he didn't clear % complete first. Now when I try to do it,
the dates jump all over the place. Many don't make sense to me based on the
constraints and dependencies.
My question is, is there a way to reset the % completes all to 0 without
having Project recalculate dates?