I seem to have a standard project manegment problem which MS project can not
handle. I run a technical project where I am receiving equipment over time
from various suppliers. I need to be able to start at task only when this
equipment is availble. I set the resource to work and input the available
from and to dates however this has no effect unless I se the work to greater
than zero even though I have alocated for example 3 units.
This is standard problem and I can not find any way to fix it