G
Gary Wright
I "PM" a technology group that has multiple projects running at the same
time, for the purposes of this email lets say 20 seperate projects.
First I created a project for my resource pool called Resource Pool (how
clever)
Second I create a Project called Tech Projects and inside of it I have 20
individual projects of various names that are all sub-projects under Tech
Projects. These projects range anywhere from 1 to 10 weeks.
The group that controls the resources tells me how much time each resource
will be able to work on each project each week. For the most part I will
only have one resource per project but very rarely will I have them 100% of
the time.
My goal - If I have a project that has 212 hours and I have a resource that
is available 20 hours week 1, 15 hours week 2, 35 hours week 3,... and so on
how would you set this up? I want to be able to tell which resources are
over allocated, and or availble for other work.
Things that I know
I have a list of all the tasks for the project anlong with project time to
complete the tasks
I have a start date
End date will be determined by resource availability
-Gary
time, for the purposes of this email lets say 20 seperate projects.
First I created a project for my resource pool called Resource Pool (how
clever)
Second I create a Project called Tech Projects and inside of it I have 20
individual projects of various names that are all sub-projects under Tech
Projects. These projects range anywhere from 1 to 10 weeks.
The group that controls the resources tells me how much time each resource
will be able to work on each project each week. For the most part I will
only have one resource per project but very rarely will I have them 100% of
the time.
My goal - If I have a project that has 212 hours and I have a resource that
is available 20 hours week 1, 15 hours week 2, 35 hours week 3,... and so on
how would you set this up? I want to be able to tell which resources are
over allocated, and or availble for other work.
Things that I know
I have a list of all the tasks for the project anlong with project time to
complete the tasks
I have a start date
End date will be determined by resource availability
-Gary