C
Cavedwella
I have tried to create a Hammock task in Project 2007 and I am getting
strange results...
I copy the Start and Finish dates of the entire project and paste them as a
link into the start and finish dates of a task called "Project Management"
I need to have the project management task stretch the entire length of the
project and any changes made to the plan update the Project management task
automatically...
When I do it this way, sometimes it adds an apparent random duration to the
task... all of a sudden the project starts in 1995 instead of 2008... snag
is... it only happens about 50% of the time...
Can someone help me understand what I am doing wrong...
Thanks
strange results...
I copy the Start and Finish dates of the entire project and paste them as a
link into the start and finish dates of a task called "Project Management"
I need to have the project management task stretch the entire length of the
project and any changes made to the plan update the Project management task
automatically...
When I do it this way, sometimes it adds an apparent random duration to the
task... all of a sudden the project starts in 1995 instead of 2008... snag
is... it only happens about 50% of the time...
Can someone help me understand what I am doing wrong...
Thanks