S
Stumped
I am looking to set up a recurring task based on working days (as opposed to
calendar days) in MS Project. For example, I have a task that occurs every
4th business day of the month. Any idea how I can set this up so that it
only looks at working time?
calendar days) in MS Project. For example, I have a task that occurs every
4th business day of the month. Any idea how I can set this up so that it
only looks at working time?