How do I set up a recurring task in Project on business days?

S

Stumped

I am looking to set up a recurring task based on working days (as opposed to
calendar days) in MS Project. For example, I have a task that occurs every
4th business day of the month. Any idea how I can set this up so that it
only looks at working time?
 
M

Mike Glen

Hi Stumped,

Welcome to this Microsoft Project newsgroup :)

Not that I know of :( I would compromise by selecting the first thursday
of each month, expanding the task to see all of the individual days, and
then adjust those that need it.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 