How do you get a 30 day look ahead for individual resources

B

bmcpherson

My management wants me to provide a report that shows the work each reource
has been assigned to accomplish in the next thirty days.

I have tried filtering by resource but this gives me all the work and I
still have to manually work the results to get an acceptable report.
 
J

Jan De Messemaeker

Hi,

The Resource Usage view gives that, and the Print... window allows you to
only show the selected period.
Hope this helps,
 
J

JulieS

Hello,

Have you tried using the "Using Resource in Date Range" filter? That should
show you only tasks assigned to the specified resource in the date range you
specify.

I hope this helps. Let us know how you get along.

Julie
 