How much cost to shorten a task?

N

Nisdav

In my project there are a number of task that have a limit of days that I can
shorten, and every day that a task can be shorten cost an amount of money.
How can I had ths columns to my project.

Cheers

David
 
J

Jan De Messemaeker

Hi David,

The only way I see to realize this is through a VBA procedure.
It should calculate the fixed cost of a task as a function of duration.
You have sufficient custom fields (like duration1, cost1, etc.) to enter the
necessary data for this formula.
HTH
 