We have installed MS Proejct 2003 and SPS. they were
integrated pretty well. But I can't understand how we can
give users possibility to edit hours worked against tasks
via Project Web access. I can edit "percent complete" on
the left pane of the tasks page but can do nothing with
cells in timesheet on the right pane. Does it requires
some additional steps or tools to be used for make it
working?
Thanks in advance.
Oleg
 
G

Guest

Have a check of your Admin settings under Admin, Customise
Project Web Access, Specify the default method for
reporting progress on tasks and Time period settings. You
probably need to select 'Hours of work done per day or per
week: Resources report the hours worked on each task
during each time period.' and 'Resources should report
their hours worked every day'.
 