Jim,
I tried this, but the duration window is giving me a hard time. I first had
to place the word "days" after my number for it to import. And once i did
that, the numbers came into project incorrectly. The duration that is in the
excel file would say 5 days, the number in the preview would show 5 days, and
the number that would import would be 13 days. I don't understand what I am
missing, I would appreciate any advice you may have.
thank you,
Brendan