how to calculate in project, work done between defined dates

I

ilan

I have a project Gantt. At the resources sheet I can view the work (effort)
and costs of the work done in the projects life-span.
I need to see how much work is done between two defined dates or between
project start to a certain defined date or a certain date to the project's
finish.
 
M

Manmeet Chaudhari

Hi Ilan,
You can make use of resource usage view which gives timephased data across
days.
By default it give you distribution of work
Goto format details and you can select more options available there to
appear on the right side of the view
Let me know if it helps

Manmeet Chaudhari
 
J

Jan De Messemaeker

Hi,

It is especially useful to show Cumulative work, then you find the work
between 2 dates as the difference between the 2 values of cum work
HTH
 