How to calculate summary progress date time on summary tasks?

G

gancev

Hi all
How to calculate summary progress date time on summary tasks?
Or if you can give me specific formula.

Thanks.
 
R

Rob Schneider

gancev said:
Hi all
How to calculate summary progress date time on summary tasks?
Or if you can give me specific formula.

Thanks.

Gancev,

Sorry, but I don't know what a "summary progress date time" is. What is
it and what is the algorithm for computing it?
 
G

gancev

Rob said:
Gancev,

Sorry, but I don't know what a "summary progress date time" is. What is
it and what is the algorithm for computing it?

"summary progress" on summary tasks on tracking gant
 
R

Rob Schneider

gancev said:
"summary progress" on summary tasks on tracking gant

If by "summary progress" you mean "% complete", or "% work complete"
(which the latter 2 are both standard Project fields), then show those
fields on the Gantt Chart View (Menu: Insert, Column and pick these two
fields). Project will compute these fields for you, so there is no need
for you to compute them. You can learn how these fields are computed by
putting the cursor on the column header, and then click on the "help"
link that appears.

By default, the Tracking Gantt view displays "% complete".
 