G
Genugenu29
I do have MS Project 2000 and I am wondering how I can separate cost for the
same resource on two different subproject using the same MS GANTT. If in the
same file I execute two activitivities, for the same resource, belonging to
two separate sub-project can I see the two cost separately ? If no, is there
a way to do it ?
Many thanks
same resource on two different subproject using the same MS GANTT. If in the
same file I execute two activitivities, for the same resource, belonging to
two separate sub-project can I see the two cost separately ? If no, is there
a way to do it ?
Many thanks