Hi, hope I can make this clear!!
A number of projects I am managing "borrow" resources from other
business groups within the organisation. Depending on the relevance
of the project to their own area they will seek to recover the costs
of these resources from the project at different rates. ie the
project will be charged a % of the full rate for those resources. The
rates can different for each resource.
An example.
Jon might work full time on a task for 10 days (Work = 10 units) but
his manager chooses to seek to recover only 80% of the cost of Jon's
time back from the project. ie True cost = 10 days effort while the
cost to the project will be only 8 days effort.
Allan works 50% on his time on the same project task for 10 days (work
= 5 units) and his manager seeks to recover only 60% of that effort.
ie 3 days effort whereas the true cost = 5 days.
What is the best way for me to estimate/track the budget and costs -
both true project cost and amount of chargeable time?
Thanks for any help.
Jon
A number of projects I am managing "borrow" resources from other
business groups within the organisation. Depending on the relevance
of the project to their own area they will seek to recover the costs
of these resources from the project at different rates. ie the
project will be charged a % of the full rate for those resources. The
rates can different for each resource.
An example.
Jon might work full time on a task for 10 days (Work = 10 units) but
his manager chooses to seek to recover only 80% of the cost of Jon's
time back from the project. ie True cost = 10 days effort while the
cost to the project will be only 8 days effort.
Allan works 50% on his time on the same project task for 10 days (work
= 5 units) and his manager seeks to recover only 60% of that effort.
ie 3 days effort whereas the true cost = 5 days.
What is the best way for me to estimate/track the budget and costs -
both true project cost and amount of chargeable time?
Thanks for any help.