How to define one of the Sat as Working day

B

Blue Fish

Hello:

May I know how can I define 21-June-2008 as working day?

Thanks a lot!
 
R

Rod Gill

Hi,

Under Tools, change working time change the standard calendar to alter the
project calendar and all resources using it (by default all of them) or
select specific resources and edit their calendars.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 