M
Michael H.
Can someone please advise best practice on how to enter a task in MS
Project that encounters multiple periods of inactivity?
Here's the scenario...
- Task has an estimate of 16 hours total effort to complete.
- Effort is spread across three days.
Day 1 = 8 hrs
Day 3 = 4 hrs
Day 5 = 4 hrs
- Days 2 and 4 are days spent waiting (no activity).
Is there a way to define the above on a single task, without setting
constraints?
Advice / thoughts greatly appreciated.
Thanks in advance.
Project that encounters multiple periods of inactivity?
Here's the scenario...
- Task has an estimate of 16 hours total effort to complete.
- Effort is spread across three days.
Day 1 = 8 hrs
Day 3 = 4 hrs
Day 5 = 4 hrs
- Days 2 and 4 are days spent waiting (no activity).
Is there a way to define the above on a single task, without setting
constraints?
Advice / thoughts greatly appreciated.
Thanks in advance.