M
mustafa
Hi All,
I have a query in Microsoft project professional 2003. How can I
update %of complete manually.
Example Scenario:
Start date: 01-Dec-08
End date : 02-Dec-08
Planned work : 16 hrs ( one resource ; 2 days)
When I enter actual effort by clicking View--„³ Resource Usage(Actual)
01- Dec-08 = 8 hrs
02-Dec-08 = 8 hrs
In this Scenario my % of complete shows that 100% completed. Whereas I
haven¡¦t complete the work
In the same time, if I go and change the Remaining work column as to
¡§2hrs¡¨, my actual work is getting changed. But this is not my expected
result. It should be like my actual hrs is 16 hrs and % complete less
than 100%(manual entry) . But the ¡§%of complete¡¨ and ¡§actualwork¡¨
columns are interlinked.
Even I have tried the below settings too¡K
Tools -„³ option-„³ calculation-„³Calculation mode (Manual)
Is there a way to update % of complete column alone?
Please apply the same scenario in MPP and help me out.
Thanks in advance.
Bye,
Mohamed Mustafa
I have a query in Microsoft project professional 2003. How can I
update %of complete manually.
Example Scenario:
Start date: 01-Dec-08
End date : 02-Dec-08
Planned work : 16 hrs ( one resource ; 2 days)
When I enter actual effort by clicking View--„³ Resource Usage(Actual)
01- Dec-08 = 8 hrs
02-Dec-08 = 8 hrs
In this Scenario my % of complete shows that 100% completed. Whereas I
haven¡¦t complete the work
In the same time, if I go and change the Remaining work column as to
¡§2hrs¡¨, my actual work is getting changed. But this is not my expected
result. It should be like my actual hrs is 16 hrs and % complete less
than 100%(manual entry) . But the ¡§%of complete¡¨ and ¡§actualwork¡¨
columns are interlinked.
Even I have tried the below settings too¡K
Tools -„³ option-„³ calculation-„³Calculation mode (Manual)
Is there a way to update % of complete column alone?
Please apply the same scenario in MPP and help me out.
Thanks in advance.
Bye,
Mohamed Mustafa