D
Doug Patrone
If a task takes 8 hours to complete and is assigned to someone with a
duration of 1 week, and now we want to shorten the duration by 2 days, but we
want the work to remain at 8 hours how can this be accomplished.
But at the same time we may want to adjust the work hours and still maintain
the 1 week duration.
We would want to see in either scenario the resource units change, not the
aforementioned (work, duration) fields. Can this be accomplished?
duration of 1 week, and now we want to shorten the duration by 2 days, but we
want the work to remain at 8 hours how can this be accomplished.
But at the same time we may want to adjust the work hours and still maintain
the 1 week duration.
We would want to see in either scenario the resource units change, not the
aforementioned (work, duration) fields. Can this be accomplished?