A
aSoundMind
Hi there,
I have a graphical indicator formula which calculates the daya
variance between current date and the baseline. The formula is working
fine. My concern is when the user manipulates the saving baseline
feature in project pro so it overwrites the previous one.
Now I want to ask how to lock that baseline so that the user can't
overwrite them. It is ok if they want to save their project baseline
to baseline1, baseline2 and so on. But the baseline field must not be
overwrite. So is it possible to achieve this and how? Thanks in
advance.
Regards,
Jack
I have a graphical indicator formula which calculates the daya
variance between current date and the baseline. The formula is working
fine. My concern is when the user manipulates the saving baseline
feature in project pro so it overwrites the previous one.
Now I want to ask how to lock that baseline so that the user can't
overwrite them. It is ok if they want to save their project baseline
to baseline1, baseline2 and so on. But the baseline field must not be
overwrite. So is it possible to achieve this and how? Thanks in
advance.
Regards,
Jack