How to print a few tasks of a project

  • Thread starter Sultan A. Ameen
  • Start date
S

Sultan A. Ameen

Dear All

Out of all the tasks in my project file, I want to print few tasks only of
my Gantt Chart View. Can you help me?

Thank you very much.
 
R

Rod Gill

Easiest way is to create a filter (see help) to show only the tasks you are
interested in. If necessary use Flag1 field to say yes to tasks you want and
create a filter to show only tasks with Flag1=Yes.
 
S

Sultan A. Ameen

Thank you very much, I did the purpose.
I wonder if there is another way like what we have in Excel as Hide and
Unhide rows.
Thank you very much again.
 
T

Trevor Rabey

Feel free to wonder, but there isn't.
Tables decide which columns show and filters determine which "rows" show.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top