Fei
I use MS Project 2007
in Project Help (duration) I read this:
"Chris is scheduled to work on the "Write proposal" task on Wednesday,
Thursday, and Friday. Jamie is scheduled to work on the "Write proposal" task
on Wednesday and Thursday. Sean is scheduled to work on the "Write proposal"
task on the following Monday and Tuesday. The working span of the "Write
proposal" task, and therefore its duration, is five days (Wednesday,
Thursday, Friday, Monday, and Tuesday)."
In this case the duration is 5 days. I have 2 questions:
1. How can I record the details of who is doing the task on which day? e.g.
if I simply gave 5 days duration for this task, later on how can I know chris
worked on wed, thur, and friday, and others worked on different days?
2. if Chris is only scheduled to workfrom 14:00 to 16:30 on Wed, and 7:00 to
11:00 on Thursday, How can I plan for this in MS Project?
thanks in advance
in Project Help (duration) I read this:
"Chris is scheduled to work on the "Write proposal" task on Wednesday,
Thursday, and Friday. Jamie is scheduled to work on the "Write proposal" task
on Wednesday and Thursday. Sean is scheduled to work on the "Write proposal"
task on the following Monday and Tuesday. The working span of the "Write
proposal" task, and therefore its duration, is five days (Wednesday,
Thursday, Friday, Monday, and Tuesday)."
In this case the duration is 5 days. I have 2 questions:
1. How can I record the details of who is doing the task on which day? e.g.
if I simply gave 5 days duration for this task, later on how can I know chris
worked on wed, thur, and friday, and others worked on different days?
2. if Chris is only scheduled to workfrom 14:00 to 16:30 on Wed, and 7:00 to
11:00 on Thursday, How can I plan for this in MS Project?
thanks in advance