how to see Fixed Costs by month?

J

Jesse

I have a task with a 12-month duration that has a $12,000 fixed cost. I'd
like to see the fixed cost by month or by quarter....like a task usage view
with cost over time. Any thoughts?
 
J

JulieS

Hello Jesse,

You can add the Cost field to the timescaled (right side) of the Task
Usage view. Click your secondary mouse button over the right side of
the view and select Cost from the shortcut menu. Then use the zoom out
button on the Standard toolbar to show the timescale portion in months.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information