I cannot seem to select more than 9 non-adjacent tasks in
MS Project 2000. Is there a parameter setting or is this
a limitation or bug within MS Project?
 
G

Gérard DUCOURET

Hello Gerry,
In fact, you can select 10 non-adjacent tasks : it's a MS Project limitation.