How to set up totalling of sub-tasks in Summary task

C

Chandra

I have a column"% Completed" and enter the % of the tasks in this field.
But the Summary field is not getting summed up the tasks % and doesnot allow
manual entry.Pl. see the example below:
% Status Descriptions.

0% Communications
100% Depatmental Meeting
100% Team Leads Meeting
0% SOA Compliance/ IT Controls
0% Testing for IT General Controls & Self-Assessment
0% Initialization of Testing Processes
60% Identify Processes
60% Identify process Owners
0% Identify the Risks in the processes
The Summary Tasks "Communications", "Initialization of Testing Procedures"
etc are not getting summed up of the sub tasks.
 
G

Gérard Ducouret

Hello Chandra,
Are you using actually the "% Complete" or the "Physical % Complete" field ?
The second one never sums up.

Another idea : aren't you in manual calculation :
Tools / Options / Calculation / choose Automatic

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question